Semester : SEMESTER 7
Subject : Electrical system design
Year : 2020
Term : SEPTEMBER
Scheme : 2015 Full Time
Course Code : EE 405
Page:2
11
12 a)
0)
13
14 a)
0)
00000EE405121901
The plan layout of a one bed room domestic building is shown below. Locate (10)
the light, fan, socket points etc., required for the electrification of the building
as per NEC requirements. Calculate (a) Connected load of the building (b)
Maximum demand in kW (c) Type of supply required (d) Number of light and
power circuits (e) Details of the distribution board selected
Toilet
Dinning room
Drawing room
kitchen
Bed room
PART C
Answer any two full questions, each carries 10 marks.
Which are the main factors to be taken into account for the selection of cables, (5)
Explain
Fault current anticipated in a location is 8000A. soil resistivity = 10 Q-m. Earth (5)
resistance is limited to 1Q. Design an earthing system. Fault duration can be
taken as 3seconds. Plate electrode of 1.2mx1.2mx12.5mm shall be used.
A 400kVA, 11kV/433V delta-star connected transformer is installed in an (10)
industry. This transformer is connected to 11kV supply through an over-head
line of length 2.5 km. The conductor used is RABBIT with an equilateral
spacing of 900 mm. The percentage reactance of the transformer is 4% and the
full load copper loss of the transformer is 2%. The three-phase short circuit
power at the utility substation is 40031۷ 8. The resistance of the line conductor
is 0.454Q/km. Calculate peak short circuit current on the primary and
secondary terminals of the transformer.
Which are the pre-commissioning tests on power transformers used in व (5)
electrical installation. Explain
An outdoor pole mounted 11kV/433 V substation has to be installed for supply (5)
to a residential area having a load of 63 kVA. With the help of a neat diagram,
make a list of materials required.
2/3