Semester : SEMESTER 5
Subject : Water Resources Engineering
Year : 2019
Term : DECEMBER
Branch : CIVIL ENGINEERING
Scheme : 2015 Full Time
Course Code : CE 309
Page:1
E192046 Pages: 3
Reg No.: Name:
Max. Marks: 100
1 a)
b)
0)
0)
0)
APJ ABDUL KALAM TECHNOLOGICAL UNIVERSITY
V SEMESTER B.TECH DEGREE EXAMINATION(R&S), DECEMBER 2019
Course Code: CE309
Course Name: WATER RESOURCES ENGINEERING
Graph sheets may be provided
PARTA
Answer any two full questions, each carries 15 marks.
A rain gauge recorded the following accumulated rainfall during a storm. Plot a
Hyetograph for the given data.
Time(am)
Accumulated
rainfall 0 2 3 7 12 19 20
(mm)
Describe how infiltration rate is measured using Double ring infiltrometer.
What is Recurrence interval? How is it determined?
The following are the ordinates of a 6 hour storm hydrograph of a catchment
area of 426 hectares.
3 8 0
Time 00.00 12noon 00.00 12noon 00.00
am pm pm
Ordinates
16 115 230 192 | 171 117 59 28 16
m/s
Construct a 6 hour unit hydrograph for the same basin , if constant base flow is
16 cumecs.
A station ‘A’ was inoperative while stations B, C, D and E registered 80 mm,
70mm, 83 mm and 79 mm of precipitation. Co-ordinates of B, C, D and E are
(7, 6), (10,-8), (-11,-5) and (-5, 5) respectively with coordinates of A as (0, 0).
Estimate storm precipitation by Inverse distance method.
A 12 hour storm rainfall with following depths in cm occurs over a basin.
3, 3.4, 8.6, 4.9, 11.5, 5, 3, 11, 5.4, 5.8, 1.6, 1.3. Surface runoff is 20.6 cm.
Determine the average infiltration index.
Duration: 3 Hours
Marks
(6)
(5)
(4)
(6)
(5)
(4)