APJ ABDUL KALAM TECHNOLOGICAL UNIVERSITY
Seventh Semester B.Tech Degree Examination (Regular and Supplementary), December 2020
Max. Marks: 100
Course Code: CE409
Course Name: QUANTITY SURVEYING & VALUATION
General Instructions: 1.Supplement answers with illustrations, wherever necessary
b)
b)
2. Assume any missing data suitably
PARTA
Answer any two full questions, each carries 10 marks.
When and where the following estimate are used (i) Annual Repair estimate
(ii) Supplementary estimate.
Outline the use of CPWD schedule of rates and how it is applied for the
construction work in the different states of India.
List out the any five items of work involved in a residential building with general
specification of the work and give the unit of measurement of each item of work.
Recall the General rules of Indian Standard(IS1200(Part-1)-1992) for the Method
of measurement of Buildings and Civil Engineering works
Develop unit rate of the work (DSR 2018 item No. 4.1.2), providing and laying in
position 1:11/%:3 (1 Cement: 112 coarse sand (zone-III) : 3 graded stone aggregate
20 mm nominal size) cement concrete of specified grade excluding the cost of
centering and shuttering - All work up to plinth level : MATERIAL : 0.57cu.m
20mm nominal size of stone aggregate © Rs.1370/cu.m., 0.28cu.m 10mm
nominal size of stone aggregate @ Rs.1350/cu.m., 0.425 cu.m of coarse sand
(1/006-111) @Rs.1350/cu.m., 0.2833cu.m Portland cement © Rs.4940/tonne,
LABOUR : 0.10 Mason © Rs.709/day; 1.63 Beldar © Rs.558/day, 0.70 Bhisti
@ Rs.617/day. CARRIAGE PROVISIONS: Stone aggregate below 40mm Rs.
103.77/cu.m.; coarse sand @Rs.103.77/cu.m. and for cement @ Rs.92.24/tonne.
HIRE CHARGES of concrete mixer [email protected]/day, Vibrator
0.07 @Rs.370/day, SUNDRIES , LS, [email protected]
PART 13
Answer any two full questions, each carries 25 marks.
Prepare a detailed measurement and calculate the material quantity of a 100m
Page 1of 4
Duration: 3 Hours
Marks
(5)
(5)
(5)
(5)
(10)
(25)