Semester : SEMESTER 7
Subject : Quantity Surveying and Valuation
Year : 2020
Term : SEPTEMBER
Branch : CIVIL ENGINEERING
Scheme : 2015 Full Time
Course Code : CE 409
Page:1
8 04000CE409092001 Pages: 4
Reg No.: Name:
APJ ABDUL KALAM TECHNOLOGICAL UNIVERSITY
Seventh semester B.Tech examinations (S), September 2020
Course Code: CE409
Course Name: QUANTITY SURVEYING AND VALUATION
Max. Marks: 100 Duration: 3 Hours
(Any missing data may be suitably assumed)
PART A
Answer any two full questions, each carries 10 marks. Marks
1 a) Explain the provisions of carriage of material calculation stipulated in CPWD schedule (6)
of rate.
0) Write the unit of measurement of (i) DPC using waterproofing compound (ii) Iron (4)
work for window (iii) Water proof painting above roof slab 11) Wood work for
frames of doors.
2 a) Calculate the amount required for carriage of 2500kg of steel reinforcement to be (6)
brought from a source of 7km away from the site. The vehicle will reach at 75m away
from the construction site.
CPWD data are as follows for mechanical transport of 1 tonne of steel at
11111 @ २5.69.93; [email protected]; [email protected]; beyond 5km upto 10km per km
@Rs.7.72 ; and for transport of 1 tonne of steel by manual labour Rs.144.20/- for first
50meters and Rs.21.16/- for every additional 50metre or part thereof.(All rate given are
inclusive of profit & overhead).
b) What are the factors considered for calculating the “cost of conveyance” for material? (4)
3 9) Work out the unit rate for the following work. (10)
Cement Concrete work, mix 1:5:10 , using 40 mm broken stone.
51.0 | Material Quantity Rate
1 Broken Stone 0.95 Cu.m
2 Sand 0.48 Cu.m
3 Cement 137 kg
4 | Mason 0.10 No.
5 Men/Women 1.00 No. Rs 650/No
Quantity one Cubic meter (1 Cu.m)